In power system, Power system restoration is a challenging task for
newlinepower system operators. It is a complex process to restore the power system
newlinewith short period of time. This research work proposes the Parallel sub-island
newlineparallel power system restoration (PPPSR) algorithm to restore the Power
newlinesystem as a faster than parallel power system restoration (PPSR). PPPSR
newlinealgorithm process is involved in the sequence of process such as, generation
newlinecapability optimization, critical load restoration and transmission path
newlinesectionalized strategy.In the first process, the generation capability optimization, searching
newlineblack-start generators source plays a vital role to initialize the process. The
newlineproposed model is develop intelligent integrated system (IIS) with Electric
newlineVehicle charging station to act as Black-start unit to provide cranking power to
newlineNon Black-Start unit. Proposed IIS system is tested by normal state and
newlinerestoration state with different case optimization module. In the second
newlineprocess, sustain the critical load at blackout period is challenging process in
newlinethe power system. Here the proposed model is modelled to avoid situation by
newlineDistributed generation (DG) with intelligence system. This system is designed
newlinein such a way that, whenever blackout occurs, DG source gives higher priority
newlineto provide power to meet critical load at any circumstances. It also tested the
newlinesystem for blackout state and normal state. The proposed method is also
newlineimplemented in intelligence system by fuzzy logic system. In the third process,
newlinethe power system restoration is done by parallel operation. So, it needs
newlinesectionalized strategies are to be used to find the shortest path from one node
newlineto another node with satisfying all the constraints. Recently developed cuckoo
newlinesearch algorithm is proposed to find the shortest path in the transmission line
newlinefor sectionalizing process. PPPSR algorithm tested in IEEE 39-bus system
newlineusing Virtual Instrumentation.