Progressive collapse is a situation where local failure of a primary structural component leads
newlineto the collapse of adjoining members, which in turn leads to spread of collapse. Progressive
newlinecollapse of building structures is initiated when one or more vertical load carrying members are
newlineseriously damaged or collapsed due to extreme loading imposed by earthquake, flood,
newlineexplosion, vehicle impact etc. As a result, a substantial part of the structure may collapse,
newlinecausing greater damage to the structure than the initial impact. Progressive collapse of any
newlinestructure causes catastrophic failure of structure and substantial loss of human lives as well as
newlinenatural resources. In order to reduce risk of progressive collapse, it is necessary to design and
newlinedetail the structure to develop alternate load path in the event of extreme loading.
newlineIn precast concrete construction, the components of structures are produced in controlled
newlineenvironment, transported and individual precast elements are connected appropriately at site.
newlineBecause of better quality control and faster rate of construction, the precast concrete
newlineconstruction is being adopted world-wide including India. However, in precast concrete
newlineconstruction, connections are the critical elements of the structure, because in past, major
newlinecollapse of precast building took place because of connection failure. Therefore, it is very
newlineimportant to study the performance of precast beam column assembly under a progressive
newlinecollapse scenario. Behaviour of precast beam column assemblies under progressive collapse
newlinecondition is not reported in greater detail in literature. National Institute of Standard and
newlineTechnology (NIST), U. S. Department of Commerce has presented report on experimental and
newlinecomputational study of two precast concrete moment-frame assemblies under a column removal
newlinescenario, in September 2015. During last couple of years, few more investigators have reported
newlineresults of experimental and numerical studies conducted on different precast beam column
newlineconnections under